Tuesday, December 03, 2013

Reno@Toa Payoh - Plastering of walls

 All the door frames are installed already!
 Plastering of newly erected walls are completed too
Above: Daughter's room
 Above: Master room
 Installation of bathroom wall tiles in progress for the common bathroom
While someone is doing the bathroom walls, the other 2 have started on the kitchen wall tiles. Next week, they will start on the living and dining floor tiles which has the largest floor area, that would need at least one week to finish all the work.

Tomorrow, we are meeting Cath Kidston Mum to settle all the electrical wirings, powerpoint and switch locations.